When Delay Equals Insolvency: How time risk helped fuel a $15bn construction failure

The Watson report into the CFMEU’s Victorian operations, and the suggested $15 billion cost to Victorian taxpayers, have prompted familiar calls for tougher regulators, stronger criminal penalties, and renewed industrial law reform. Yet one of its most important lessons lies elsewhere. The power Watson describes did not arise from statute, nor from any legal monopoly over enterprise bargaining. It arose from something more prosaic and more dangerous: time risk.

On major public construction projects, delay is not merely inconvenient. It can be fatal to a contractor’s balance sheet. Liquidated damages (LDs), financing costs, termination exposure and cascading subcontract claims mean that even short disruptions can push a contractor towards insolvency. Watson’s “Rotting from the Top” report shows how this reality created the conditions for blackmail, extortion and corruption. When delay equals insolvency, delay itself becomes a tool of coercion.

If governments are serious about reducing the opportunities for the conduct Watson documents, they should look first not to the Fair Work Act, but to their own construction contracts. In particular, they should broaden extension-of-time (EOT) events to cover site- and contractor-specific industrial action, not just sector‑wide industrial action. Doing so would strike directly at the economic pressure that made corruption pay. The most effective response, therefore, is not to expand industrial regulation, but to redesign the contractual allocation of time risk on public projects.

The Watson diagnosis: power built on time pressure

A striking feature of the Watson report is how little it relies on formal legal structures to explain the CFMEU’s influence. There is no statutory requirement for contractors to hold an enterprise agreement. There is no legislative provision granting unions a veto over EBAs. Enterprise agreements are approved by the Fair Work Commission, not unions.

Instead, Watson describes a system in which access to labour and industrial peace was controlled at site level, and where the cost of delay was catastrophic. Site shutdowns and disruptions to concrete pours did not need to be prolonged to be devastating. Against that background, EBAs became de facto “licences to operate”, and a black market emerged in facilitating them quickly. Contractors paid for them not because the law required it, but because time did.

This is the central insight. The conduct Watson describes was not enabled by excessive legal rights; it was enabled by risk asymmetry. Industrial actors could impose delay at relatively low marginal cost to themselves, while contractors bore extreme financial exposure. That imbalance turned delay into leverage, and leverage into corruption.

Why existing EOT regimes don’t neutralise the risk

Most government construction contracts already acknowledge industrial action as a relevant risk. But in practice, EOT regimes often fail to disarm the pressure Watson identifies.

Industrial action is frequently sliced into artificial categories: protected versus unprotected, sector‑wide versus site‑specific, avoidable versus unavoidable. Relief is often confined to narrow classes of industrial action, leaving contractors exposed where pressure is most acute — at the individual site or contractor level.

Even where industrial action qualifies as an EOT event, relief is usually subject to strict notice, proof and causation requirements. Those mechanisms may be appropriate for ordinary delay claims, but they sit uneasily with fast‑moving industrial disputes. Contractors may face LD exposure while their claim for an EOT is assessed or disputed, preserving the very time pressure that enables coercion.

Critically, EOT relief typically addresses time but not cost. Financing expenses, prolongation costs and resource inefficiencies continue to accrue. The contractor remains worse off the longer disruption persists.

In short, many existing EOT regimes recognise industrial action without meaningfully neutralising it as a weapon to extort.

A broader EOT event: simple, targeted, effective

The reform required is conceptually simple. Government construction contracts should include a broad EOT event for industrial action beyond the contractor’s reasonable control, expressly including site‑specific and contractor‑specific industrial action, whether protected or not.

The EOT clause could also operate automatically to extend the date for practical completion by the period of subsequently verified disruption. During that period, LDs would not accrue. The contractor would remain obliged to mitigate delay where reasonably possible, but would not face insolvency merely for being the target of industrial pressure.

This does not legitimise unlawful conduct. It removes its most powerful commercial leverage.

Why site‑specific coverage is essential

Some argue that EOT relief should be confined to large‑scale or sector‑wide industrial action, on the basis that site‑specific disputes are more “within the contractor’s control”. Watson’s findings suggest the opposite.

It was precisely targeted, site‑level pressure — strategic stoppages, threats of disruption, deliberate bargaining delay — that proved most coercive. Limiting relief to general strikes leaves the sharpest tool untouched.

Contractors are often poorly placed to control site‑specific industrial action on major public projects with dense union presence and critical‑path sensitivity. Treating such events as a contractor risk ignores commercial reality and perpetuates the asymmetry Watson identifies.

The obvious objection: won’t contractors manufacture industrial action?

A predictable criticism of broader EOT relief is that incompetent contractors will “manufacture” industrial action to escape LD liability for their own delay.

That concern misunderstands both how EOTs operate and how contractors behave.

First, causation remains central. An EOT is only available for delay to completion caused by industrial action. If the critical path is already delayed by contractor default, poor planning or under‑resourcing, industrial disruption will not excuse that delay. Properly administered EOT regimes already distinguish between qualifying and non‑qualifying delay; a broader industrial action event does not change that discipline.  An EOT for industrial action does not excuse defective work, inadequate resourcing, or failure to mitigate delay.

Secondly, EOT relief addresses time, not money. Even if LDs are suspended, the contractor continues to incur prolongation costs, financing expenses, overheads and inefficiencies for every day of disruption. Industrial action is commercially painful for contractors. It is not in their interest to prolong it, let alone manufacture it.

Thirdly, the suggestion that contractors can readily engineer industrial disputes ignores the asymmetry Watson exposes. Contractors were not initiating industrial action; they were responding to it under extreme pressure. Removing LD exposure does not create a new incentive to delay — it removes an incentive to pay bribes or accede to improper demands.

Finally, government principals retain ample tools to address genuine incompetence: performance security, step‑in rights, termination for default and reputational consequences in future procurements. Broadening EOT relief does not deprive principals of these protections.

Why this reform is both modest and powerful

Compared with structural industrial law reform, redesigning EOT clauses is modest. It requires no change to the Fair Work Act. It does not diminish lawful union activity. It sits squarely within governments’ role as contracting principals.

Yet it is powerful because it targets incentives rather than symptoms. It removes the financial hostage that made extortion viable. It makes resistance to coercion commercially rational.

Governments are also the parties best placed to bear systemic industrial risk on public projects. Watson has publicly argued that the failure to address this risk in Victoria may have cost taxpayers $15 billion. Where the principal’s real exposure to delay is political, social or reputational — rather than direct financial loss — insisting that individual contractors carry insolvency-level time risk is neither efficient nor defensible.

The broader lesson

The Watson report reminds us that corruption rarely flourishes because the law is permissive. It flourishes where pressure points exist — where risk is concentrated and time is weaponised.

By broadening EOT events to cover site- and contractor-specific industrial action, governments can defuse one of the most potent pressure points in the construction industry. They can ensure that industrial disruption remains costly, but not fatal; disruptive, but not coercive.

When delay from industrial action no longer equals insolvency, much of the coercive power Watson describes simply evaporates.


What do you think? Share your thoughts via the comments section below.

Owen Hayford

Specialist infrastructure lawyer and commercial advisor

https://www.infralegal.com.au
Next
Next

GICCA’s first Delivery Contractor tender gives us a steer on its preferred delivery model